Cable placement Baltic 1+2, Baltic Sea

Grid connection

We were able to implement the engineering and construction for laying the sea cable with Ø 236 mm from the seabed to the transformer platform for the wind farms Baltic I and Baltic II.

The three-conductor cable with integrated fiberglass had to be pulled up vertically 30 meters. The special roller bend and high-strength box rollers pulled the cable to the end closures. A grid platform serves as a sufficiently long reserve loop.

A large deflection wheel that was installed above the platform was able to implement insertion of the cable.

Technical data

Plant the platforms Insertion of 4 connection cables 151/152/153/154 from the seabed to
Cable Ø 236 mm / 3 conductor sea cable with fiberglass
Cable weight 56.6 kg / meter
Winch type Habegger
Deflection pulleys for cable pull 1.2 m Ø
Inclination 0° - 90°
Phase distance 70 mm
Data protection notice
This website uses external components which can be used to collect data about your behaviour. about your behaviour. Read more about this in our data protection information.
Necessary cookies are always loaded