Steel water construction power plant, Hinterdorf Engi

Entire steel water construction equipment

We were able to deliver the entire steel water construction equipment for the new power plant in Hinterdorf an der Sernf in Engi.

We implemented the following components in this project:

Technical data

Shutter 12.2 x 1.2 m
Inlet protectors 7.5 x 7 m
Basic drain protectors 3.3 x 3 m
Flushing protectors 1.5 x 1.2 m
Fish exit protectors 2.5 x 0.5 m
Inlet rake 5.2 x 2.4 m
Telescope a. rake cleaning machine 5.2 x 2.4 m